Below you can browse some of our recent projects.
Value: £9.2M
Togher Construction Limited constructed two x 7-storey tower blocks and one x 12-storey tower block, reaching 70m tall, including a basement level. The ground, first and second floors accommodate phase 2 of Ark Soane Academy, a new 1,200-place secondary school. 113 residential properties have been constructed on the upper levels, in addition to three separate townhouses which we laid the foundations.
Value: £6.1M
Axion House Lewisham is a planned mixed-use development in the heart of Lewisham town centre.
1, 2, and 3 bedroom apartments next to Ravensbourne River.
The site will deliver 141 new homes.
Value: £9.3M
Beam Park is a development of residential homes and expanded community in Rainham to the south of Dagenham centre. We constructed 8 blocks over a 12 month period.
Value: £9.7M
Our works consisted of building 6 blocks, the tallest being 21 floors and due to crane restrictions, used an intricate slipform system to construct it.
Value: £7.1M
Consisting of 8 Low rise buildings enabling 105 homes and the foundations for four-bedroom houses. Phase 2a due for completion in February 2024.
Value: £1.15m
Togher Construction built 12 studio apartments for artists and their families in Barking, east London with an exceptional concrete finish.
Value: £18.2M
Meridian Water is a £6 billion regeneration of the area. Phase 1a consists of 5 blocks, the highest being 12 floors, and we also installed all the sitewide services for the entirety of Phase 1a.
Value: £11.9M
A development in the picturesque setting of Walton on Thames, we built one large block consisting of 375 apartments and a substantial basement.
Value: £5.9M
Completed in January 2018, a 9 storey 20.00m2 scheme consisting of 194 units.
Usage includes the client's new regional offices, commercial area and car parking. The upper levels provide residential and social units.
Value: £5.2M
Two blocks consisting of 166 units. Works include sewer diversion, new road, groundworks and concrete frame on a commercial and residential scheme.
Value: £4.7M
Deep drainage, groundworks and RC frame on a 4,000m2 footprint rising to 6 storeys to provide 106 units including all external hard and soft landscaping.
Value: £9.7M
A six storey waterproof basement below the water table in Bromley town centre. Works consisted of multi-level car park, new bus route, major temporary works and enhanced concrete finishes.
Value: £3.8M
This is a top down construction method for the substructure and basement of a 26 storey building on a confined site. Where the 3,000m2 basement raft slab was poured in 2 continuous concrete pours in a logistically challenging location next to London bridge station and the Shard.
Value: £8.1M
Client: McCabe Builders (UK) Ltd
Contract Period: 78 Weeks
Substructure: Bulk excavation, inclusive of substantial temporary works due to the proximity of a major arterial route within the centre of London. Other sub-structure works included complicated underpinning, and traditional basement works. This incorporated the waterproofing of the structure, up to ground floor to complete the basement car park.
Superstructure: A 27 storey concrete frame constructed using a post tension system to make substantial savings on reinforcement, concrete and programme. A jump-form system was used on the main stair/lift core to create extra space on site and make time on the project.
Value: £2.7M
Concrete structure build on vibration proof pads incorporated in the substructure working around façade and pod installation followed by a high quality external works scheme.
Value: 2.4M
13 storey frame incorporating triple panoramic lift shaft. Constructed as jump form with bespoke pre-assembled formwork to produce architectural concrete fair face finish
Value: £8.3M
Both phases covered over 40,000m2 of floor area, single storey sheet piled basement of 6,000m2 , various multi-level medium rise RC frames and a comprehensive external works package.
Value: £4.8M
Works included bulk dig, temporary works, basement construction, two 6 storey RC frames and a very extensive external works package. This was a logistically challenging project due to the neighbouring school and coordinating around drop off and pick up times.
Value: £1.9M
Client: Octavia Housing
Main Contractor: Willmott Dixon
Engineer: Tully De'Ath Architect: HuntersMarket
Contract Period: 28 Weeks
Value: £1.9M
Client: Poplar Harca
Main Contractor: Countryside Properties
Engineer: Brand Leonard
Architect: Watkins Gray International
Contract Period: 25 weeks
Togher Construction have completed both phases of this 480 unit development for Countryside Properties. The east London scheme consists of 6 reinforced concrete frames of varying heights and over 10,000 m2 of soffit.
"Togher displayed their experience and knowledge on this challenging scheme, they were always proactive and easy to deal with. I would have no hesitation in recommending them on future projects."
"On a substantial package like this Togher proved themselves to be the right choice for us and I would not hesitate to use them on future projects."